LEMERY, BATANGAS | |||||||||
---|---|---|---|---|---|---|---|---|---|
SURVEYED PAVEMENT DISTRESS IN J.P. RIZAL STREET | |||||||||
Defect(s)/Deficiencies | Estimated Quantity | Unit of Measure | Remarks | Length | Width | Depth | No. of Slab | Latitude | Longitude |
Total: 101 | |||||||||
Pothole | 0.2444 | sq. m | 47 cm | 52 cm | 1.5 cm | 2 | 13.88082 | 120.9184 | |
Major wornout surface | 27.9 | sq. m | 9 | 13.8806 | 120.9179 | ||||
Concrete Pavement/E | 19 | 13.88044 | 120.9178 | ||||||
Asphalt Pavement/S | 20 | 13.88044 | 120.9178 | ||||||
Asphalt Pavement/E; Ilustre Ave. Brgy 2/In | 13.88024 | 120.9171 | |||||||
Brgy Rizal - J.P. Rizal St/In | 13.879356 | 120.9164 | |||||||
Joint Spalling | 0.93 | sq. m | 3.1 m | 30 cm | 6 cm | 7 | 13.880275 | 120.916681 | |
Independencia St/In | 12 | 13.879303 | 120.916007 | ||||||
Minor wornout | 167.4 | sq. m | 13 | 13.87893 | 120.91564 | ||||
M.H. Del Pilar/In | 19 | 13.878902 | 102.915543 | ||||||
Major wornout | 27.9 | sq. m | 20 | ||||||
Pothole (delamination) | 0.075 | sq. m | 3m | 2.5 cm | 1.5 cm | 30 | 13.878618 | 120.915097 | |
Sangalang St/In | 42 | 13.879733 | 120.915052 | ||||||
Minor wornout | 27.9 | sq. m | 43 | 13.879518 | 120.915751 | ||||
Union St/In | 54 | 13.878045 | 120.914176 | ||||||
Major Wornout Surface | 27.9 | sq. m | 77 | 13.87797 | 120.913974 | ||||
Don Conchita St/Co | 101 | 13.877266 | 120.9129 | ||||||
Note: | Legend: | /S - Start | |||||||
1. The data is surveyed last February 16, 2022. | /E - End | ||||||||
2. The unit of measure l.m denotes linear meter. | /In - Intersection | ||||||||
/Co - Corner |